Phase I Costs
-
Information as of March 2019
Nearly all projects in the first phase have been bid and approved by the Board of Education. At this point in time, project costs are more than $2 million under the original estimates developed more than one year ago.
-
Project List
Cost Estimate
Actual Bid Amount
MVHS Construction Costs
$23,711,969
$20,240,746
MVHS Soft Costs
====
$3,348,788†
List of MVHS Projects
MVHS Storm Water Management
New Competition Gym
New Theatre
South Field House Addition
Increased Weight Room Space
Increased Wrestling Room Space
Repurpose Existing TheatreOther Projects
Classroom Audio/Visual Upgrade $2,159,500
$911,125
Door Access System
(Safety and Security)$244,500
$20,058*
*(Only front door remote access audio/video controls are completed. Remaining door access system will commence when other security systems are completed.)Security Camera Replacement $920,000
$573,891
IP Mass Notification System $1,137,600
$762,419 Upgrade Handheld Radio System $145,000
145,385
Front Office Doors; Security Upgrade $49,000
Planning in progress.
Renovate Elem. Playgrounds (CCE, ME, SSE) $1,369,270
$1,292,415
TOTAL COSTS
Phase I to date$29,736,839
$27,294,827
†Estimated costs