Phase I Costs

  • Information as of March 2019

    Nearly all projects in the first phase have been bid and approved by the Board of Education. At this point in time, project costs are more than $2 million under the original estimates developed more than one year ago.

  •  Project List

    Cost Estimate

    Actual Bid Amount

     MVHS Construction Costs

    $23,711,969

    $20,240,746

     MVHS Soft Costs

    ====

    $3,348,788†

     List of MVHS Projects
       MVHS Storm Water Management
       New Competition Gym
       New Theatre
       South Field House Addition
       Increased Weight Room Space
       Increased  Wrestling Room Space
       Repurpose Existing Theatre

     

     

     Other Projects

     Classroom Audio/Visual Upgrade

    $2,159,500

    $911,125

     Door Access System 
     (Safety and Security)

    $244,500

    $20,058*
    *(Only front door remote access audio/video controls are completed. Remaining door access system will commence when other security systems are completed.)

     Security Camera Replacement

    $920,000

    $573,891

     IP Mass Notification System

    $1,137,600

    $762,419
     Upgrade Handheld Radio System

    $145,000

    145,385

     Front Office Doors; Security Upgrade

    $49,000

    Planning in progress.

     Renovate Elem. Playgrounds (CCE, ME,  SSE)

    $1,369,270

    $1,292,415

      TOTAL COSTS
      Phase I to date

    $29,736,839

    $27,294,827

    †Estimated costs